The shareholders demanded 1.3 million from the developer "Smolt" for delaying the delivery of the apartments in Vladivostok.
The money was received by two people from the special developer Samolet-Sabaneev, owned by the federal entrepreneur Samolet.
The lawsuit was filed due to a delay in the construction and issuance of keys to the apartments in the Savannah 125 residential complex. They wanted to deliver it in December 2025, but in the end the date was moved. The material of the case shows that citizens B and T purchased an apartment with an area of 39 square meters for 7.5 million rubles.
The deadline for completion was delayed by 174 days, and the shareholders demanded 1.5 million rubles in fines, 192 thousand rubles spent on rent as well as compensation for moral damages and a fine to the company.
In response, the developer gave his calculation of the fine, which turned out to be lower than what the shareholders demanded.
The court decided that it is necessary to return 1.3 million rubles from Smolt for two shareholders, as well as compensate them with 10 thousand rubles for moral damage. Also, the company must pay a state fee of 22,000 rubles and pay a fine of 33,000 rubles for each applicant.
According to the "Golden Bridge" publication.