The energy workers of the Gomel region are entering the finish line in the execution of one of the largest infrastructure projects in the region - the construction of a 330 kilowatt high voltage line "Mozir - Patrikov - Mikashvichi".
The length of the new electricity transmission line is about 150 kilometers; It will connect Gomel and Brest regions. At the moment, the construction and installation work is almost finished, specialists are carrying out ordering operations. In accordance with the instructions of the head of state, all phases of the facility are planned to be fully completed by the end of December 2026. At the same time, the reconstruction of two central substations - Mozir and Mikshebichi - is being completed.
When will the "Mozir-Mikshevici" high voltage line operate at full capacity?
The "Positive Agenda" program will tell you.