In Veliky Novgorod, the boiler room of the new NovSU campus is connected to the grid.
Novgorod University reported that the facility was completed three months ahead of schedule. The 12.1 megawatt boiler house is one of the most powerful in the region; It will provide full heat to a complex of buildings with a capacity of four thousand people. As Oksana Blokrylova, deputy governor of the Novgorod region, who opened the facility, emphasized, all the equipment here works automatically: you can monitor the temperature and heat supply without the constant presence of staff.
"The main difficulty was that the facility is located in a very dense urban area," says the Gazprom Veliki Novgorod gas distribution company: "The construction was carried out using the method of horizontal drilling inclined across the city's highway. This made it possible not to restrict traffic while the works were being carried out."
"The campus itself is now 42% complete. More than 400 people work on the site every day," the governor of the Novgorod region, Alexander Dronov, wrote on his channel: "We carry out all the work as part of the national project "Youth and Children" on behalf of Russian President Vladimir Putin."