More than 2/3 of the market participants do not have enough capacity for data centers.
Over the past year, 64% of Russian market participants encountered power shortages during the construction or expansion of data centers, Kommersant reports citing High Energy Research. The lack of available capacity was cited by 48.5% of respondents as the main obstacle to establishing new facilities. 33% stated that it takes time to connect to electricity grids, and 27.8% stated its high cost.
Because of a lack of power, 33.8% of respondents postponed the launch of a data center, and 16.2% began to build a less powerful facility. Another 8.2% stopped construction, and 2.8% abandoned projects altogether.
A little more than a fifth of the respondents allocated additional funds to the energy sector to support projects. 12.7% of the respondents chose their own generation, another 37.9% are studying this option. Projects have already transferred 6.4% to areas with spare capacity.
The popularity of DIY has been growing over the past few years. As Maxim Zagornov pointed out, it is increasingly seen not as a reserve in case of an accident, but as part of the production infrastructure. At the same time, decentralized production should not compete with centralized energy, but complement it.