In Adygea, the first two stages of the Ramat Gozrifal - Lagunki route, 7.7 km long, are ready for operation. The construction progress was discussed by the Deputy Minister of Construction and Housing and Community Services of the Russian Federation Yuri Gurdaev during a working visit. The new road will cut the route to the tourist areas in half. The third phase, 7.4 km long, is now underway: in the highlands, workers will have to build more than 2.5 km of reinforced concrete retaining walls, strengthen the landslide slopes and build a permanent bridge across the Jolovnia River, taking into account seismic requirements.