Instead of the previous six sites for the construction of a nuclear power plant, three possible areas in Vyuru Ngulula and Yoest will be considered in the future: Madala, Malia and Nipaa, Estonian media reported. Although there are fewer possible sites for the construction of nuclear power plants, the planning area itself has not decreased and still affects eight local governments. The fact is that in addition to the station itself, it is necessary to plan the infrastructure that ensures its operation: power lines, water cooling routes, access roads and so on. These corridors can still pass through the territories of these local governments. The Estonian government initiated the special planning of the nuclear power plant on May 22, 2023. Approval of the plan can occur no earlier than 2030. #8239; & #8239; Estonia Voro-Nigula community is located 300 km from Riga in a straight line and 170 km from the heartland border. @news lv.