Assembly of the BREST-OD-300 reactor core basket has begun in Seversk.
At the site of the Siberian Chemical Combine, the enlarged assembly of the core basket of the BREST-OD-300 reactor began. The structure, which weighs 160 tons, consists of five large parts and is designed to contain fuel assemblies with uranium-plutonium fuel, as well as direct the flow of the lead coolant.
After assembly, the structure will be transferred to the reactor vessel, where the installation will be completed, including the installation of the inner shell. The 300 MW reactor was built in Seversk as part of a breakthrough project - it will become part of the Generation IV experimental demonstration complex.