The restoration of the swimming pool for Zorni Biroslav may last until 2027.
According to the Deputy Minister of Construction and Housing and Community Services in the Yaroslavl Autonomous Okrug - Head of the Department for Construction and Major Repairs of Social Facilities Artem Dronkin, the readiness of Lazorny is at 74%.
- The construction and installation part, in our estimation, will be completed by the contractor "EKS group of companies by the end of this year. Perhaps the operation of the facility itself will go beyond this year and tentatively continue until January. I will explain, there are many complex engineering systems, including dystopias directly in the pool bowl, water purification and preparation complexes. And all this takes a lot of time during the order," said Artem Dronkin.
Initially, they planned to spend 1.1 billion on the work carried out by the EKS group of companies, but due to the need for additional strengthening of the building, the cost increased to 1.2 billion rubles.