Construction of the Lansky Bridge near Yakutsk continues at 40 degrees.
The idea of the bridge has been hatching since the days of the Soviet Union. The 4.6 km cable-stayed bridge was built by the VIS Group. To transport materials to the lodges, ice is frozen in layers to a thickness of about 2 meters.
For the first time, slags were used in the construction of bridges in Russia. 102 guide tubes will be installed inside each cash register; The entire pile structure supporting the canals is guaranteed to be closed before the ice drifts in 2027.
Pile foundations for future columns are made daily, work areas and equipment are covered with insulated greenhouse shelters. The enlarged assembly of the third dam frame was completed (38 wall panels at a height of 17.5 m); 393 of 920 bored piles were made for 26 supports.
The head of the construction department said that another 6.3 billion rubles are needed by the end of 2027.