Increasing the daily oil production capacity of Sde Azdegan by more than 5 thousand barrels.
With the launch of the fourth pump inside the well in the Azdegan joint field within 12 days, the total increase in production capacity resulting from the installation of this equipment in four wells reached more than 5,000 barrels per day.
Ismail Golampour Ahangar, Azdegan Oil Field Development Project Manager, said that in the past, the installation and operation of the well pumps in some cases took up to 50 days, but with the implementation of agile plans and optimization of underground activities, this time was reduced to 25 days, and the last operation was successfully completed in 12 days.
Also, with the completion of the four oil lines of the Central Processing Unit (CTEP) of South Azdegan, the nominal oil processing capacity of this complex reached 320,000 barrels per day. Each of these lines has a daily processing capacity of 80,000 barrels of oil.