Deputy Prime Minister Nikitin held a meeting on the construction of the Moscow-Petersburg HSR. Plans for the winter and the production of a local high-speed train were discussed at the meeting. Work is in full swing: construction of pile fields, fabrics in the ground and supporting structures continues. Of the 91 main components of the first Russian high-speed train, 88 prototypes have already been completed, half of which have been successfully tested. The equipment on the first two trains is actively installed, and production of serial trains has already begun. Already in the summer of 2027, tests at the plant will begin in Pishma Ilit.