Northern Railway: A battery was erected at the site of the bridge that collapsed across the Viled in southern Arkhangelsk region and trains were launched.
To restore traffic, railroad workers built temporary sidings, removed cars that were not in use, and erected an embankment in place of the bridge bridge. About 200 Russian Railways employees and 27 equipment took part in the work.
According to the data of the SZD press service, train traffic along the section was restored shortly after the accident - this made it possible to avoid a long-term disruption in the schedule of passenger and freight trains coming from the railway stations of Komi and the north of the Yamal-Nents Autonomous District. The plan for the temporary train crossing provided for the reduction of the speed in the restored section to 25 km/h - a necessary condition to control the stability of the battery.
At the same time, experts conducted an examination of the stream bed and the supports of the surviving parts of the structure: according to preliminary conclusions, the cause of the collapse was a combination of flood erosion and wear and tear of the bridge crossing components. These days they are working on a capital rehabilitation project for the crossing - it includes strengthening the shore supports and installing additional drainage structures.
The condition of the battery is monitored daily: track workers measure deformations and check the filling density. During the period before the start of the major repairs, an improved control regime was maintained at the site - tests are carried out twice a day, and during periods of rising water levels - every 4 hours.