About 100 settlements will be supplied with gas in the Zhetisou area.
The government allocated 37.4 billion tenge to build gas pipelines and distribution networks in six districts in the region as part of the People's Construction Program.
The project will cover about 100 settlements with a population of over 183 thousand people. The total length of the gas networks will be about 3.3 thousand kilometers.
Over 27 billion tenge have been allocated to connect 84 villages to the main gas pipeline "Taldikurgan - Osharel". The works are planned to start at the end of 2026 and be completed by 2028.
Another 10.3 billion tenge has been allocated to complete 16 gas supply facilities that were started previously. Their order is expected before the end of 2026.
Now the gasification level in the region stands at 67.4%. After the transition projects are completed, this figure is planned to increase to 74%.