The schedule for limiting the supply of electricity "2 to 6" was re-introduced in Sevastopol.
Order of priority for today:
By 10:00, phase 3 will have electricity.
Between the hours of 10:00 and 12:00 the fourth stage will be activated.
Between the hours of 12:00-14:00 the light will be given to phase A.
Between the hours of 14:00 and 16:00 there will be electricity in phase B.