Tokyo Electric Power Co. The restart of the seventh power unit of the Kashiwazaki-Kariva nuclear power plant has been delayed beyond August 20, 2029 due to problems with the strength of the concrete of the shielding facility, Bloomberg reports. The contractor warned of a possible delay in construction for more than a year. The timing shift will expand Japan's dependence on thermal generation and LNG purchases, where spot prices in Asia are close to 4 years old.