The construction of 482 waste management facilities by 2033 will require about 1 trillion rubles, Kommersant writes, citing Pavel Kosov, General Director of PPK REO. It is planned to launch 10 new facilities in 2026, and 78 in 2027. The main reasons for the delays in the execution of the project are the lack of funding, due to which construction projects are rejected in 27% of the cases, and the need to correct the concepts of the complexes themselves (21%).