The Finnish municipality of Parikala plans to ban the construction of battery energy storage facilities with a capacity of more than 2 megawatts for five years. A similar ban was introduced in Mikkeli in February this year and was tested in several other municipalities.
In the fall, Finland's Ministry of Employment and the Economy began drafting legislation that would move large data centers to the back of the grid connection queue.
The planned changes activated the consumers and the municipality of Parikala is no exception. The situation in the region is complicated due to the large number of large electricity consumers. The capacity of electrical networks is not designed for such loads. They write that "there is only one main transmission line in Parikala, and its connected capacity will only be about 20 MW".