In 2026, about 97.7 billion rubles were allocated for road works in Tatarstan. This is 15.5 billion rubles, or almost 19%, more than a year earlier. The bulk of the funds - 85.2 billion rubles - came from the regional budget, and another 12.4 billion rubles were allocated by the federal center.

תרגם לעברית

Неудаща · · Source

In 2026, about 97.7 billion rubles were allocated for road works in Tatarstan. This is 15.5 billion rubles, or almost 19%, more than a year earlier. The bulk of the funds - 85.2 billion rubles - came from the regional budget, and another 12.4 billion rubles were allocated by the federal center.

In 2026, about 97.7 billion rubles were allocated for road works in Tatarstan. This is 15.5 billion rubles, or almost 19%, more than a year earlier. The bulk of the funds - 85.2 billion rubles - came from the regional budget, and another 12.4 billion rubles were allocated by the federal center.

The largest expenses within the national project "Infrastructure for Life" fell on three municipal associations. In the Kazan agglomeration 2 billion rubles were allocated for 19 objects, in Navraznia Chelyny - 1.36 billion rubles for four objects, in Nizhnekamsk - 480 million rubles for three objects.

6.3 billion rubles were allocated for the construction and reconstruction of public roads for 32 objects. So far, about 6.1 billion rubles have been distributed. The works continued on seven roads. Of the total amount, 1.72 billion rubles were allocated for new construction, 4.63 billion rubles for reconstruction.

Another 14.4 billion rubles. Assigned to road repairs and renovation. According to the data of the Ministry of Transport of Tatarstan, it is these works that provide the most noticeable increase in the part of the roads that meet the regulatory requirements. By the end of 2026 the figure should be 53.9%, and by 2030 - at least 60%.

In 2020, expenditures in the "road facilities" section amounted to approximately 47 billion rubles. In 2021, they grew to almost 98.9 billion rubles, but this amount included large federal projects, including the construction of the M-12 highway.

In 2022, 80.9 billion rubles were allocated to the regional road work program; Another 124 billion rubles were transferred to federal projects, mainly for the construction of the M-12 and the bypass of Nizhnekamsk and Navrazhenya Chelny. As a result, the total volume of road work in the republic reached 204.9 billion rubles.

In 2023, funding for the road program amounted to 90.7 billion rubles, in 2024 - about 82.9 billion rubles, in 2025 82.2 billion rubles were allocated for the repair and construction of regional and local roads. Thus, after a decrease in spending in 2024–2025, funding increases again significantly in 2026.