The first phase of the construction of a large solar power plant in Jihun is almost complete. The project covers an area of 748 dunams and is divided into two phases, the press service of the Katlon administration reported. As part of the first phase, a substation and eight sections of solar panels with a capacity of 50 MW are installed. At the same time, the construction of the central buildings, the installation of an external 220 kW switch and the first electrical transformer are underway. As experts have stated, the work is 95% complete. After that, the remaining 200 MW generation capacity will be installed.