The green branch of the metro in Kyiv can resume traffic between the right and left bank within 2-3 months, - Kalashnik.
"The estimated time frame for the restoration of metro traffic on the southern bridge is 2-3 months. The southern bridge is communal and the works will be carried out at the expense of the municipality's budget, perhaps even in the subway itself," said Minister of Infrastructure and Transport Mykola Kalachnik.
As a reminder, the Syretsko-Pecherska (green) branch of the Kyiv Metro is currently not operating between the Slavutych and "Vidovichi" stations due to damage to the infrastructure on the southern bridge due to shelling.