Data centers and reactors will be billed for unused electricity.

תרגם לעברית

КБ. экономика · · Source

Data centers and reactors will be billed for unused electricity.

The Ministry of Energy proposed to introduce the "take or pay" principle of payment for electricity to data centers and mining companies starting January 1, 2027. According to the initiative, property owners will have to pay at least 70% of the declared power when connecting to the electricity grid, regardless of actual consumption.

The requirements are planned to be extended to data centers and mining sites with a power of 670 kW and above. For installations with a capacity of up to 5 MW, a minimum payment of 70% is expected to be established immediately after the new rules come into force.