Delivery of pavilions will begin on December 1st, but construction is not yet complete.
As early as December 1st, EXPO 2027 participants should start receiving the keys to pavilions in Sorsin, Belgrade. But the construction is still not finished, and its allowance has slowed.
The entire complex will not be rented at once. The pavilions will be moved gradually, with the completion of the work and the completion of the documents.
The advisor of EXPO 2027 director Dušan Borovčanin admits: the construction is progressing slower than planned. In some pavilions, the facades and decoration are still complete, in others the interior is still being completed. By November 20, less than 10% of participants had applied for temporary building permits. This means that most countries are not yet ready to host their pavilions.
At the same time, the EXPO 2027 company itself is not engaged in construction. It is responsible for organizing the exhibition and its program, and the construction of buildings and infrastructure is entrusted to other government agencies and contractors, including the Serbian Construction Directorate.
Why is construction stalled?
Forbes Serbia lists problems with subcontractors' bank guarantees among the possible reasons for the delays. According to the publication, some of the companies worked with Alta Banca's guarantees and are now looking for other banks. Not everyone can solve this problem quickly.
Another factor is political uncertainty and changes within the EXPO company. The contractors do not understand how the project will develop and what decisions to expect from the new government.
Estimates regarding the readiness of the compound also vary greatly. On November 17, Borobanin announced that the construction work was 85% complete. The engineer Daniel Dashic, commenting on Danas, estimated the readiness according to German DIN standards at only 54-61%. According to him, not only the finish remains unfinished, but also some of the engineering systems and infrastructure.
BIE warns.
The International Bureau of Exhibitions confirms that delivery of the pavilions should begin on December 1st. But they warn that each day of delay takes time from the states to provide equipment, set up and prepare exhibits.