The company for production of Siberia responded to the publication about sloppy landscaping at the site of network replacement works in the center of Novosibirsk - at the intersection of Vokselanya Magestrel and Dimitrov Boulevard. "The improvement of the Koli highway will be fully completed no later than November 9," the press service of SGK-Novosibirsk told Siberia Express. "In the first stage [of the work], 166 meters of pipes were replaced in single-pipe terms, as well as two thermal cells. In the second phase, another 245 meters of pipes were laid, and two thermal cells were modernized, the SGK said. - The heat supply of 77 facilities, including 37 apartment buildings, depends on the old heating facilities of one Dimiba. Pipes in two sections along Dimitrov Boulevard were 35 years as of 2020, more than 26 defects were eliminated here.