◂ The Directorate for Technical Services in the Aleppo Governorate has completed approximately 95% of the insulation work on the route of the Quek River, a length of approximately five kilometers, starting from the treatment station in Sheikh Said to the Bustan Al-Qasr bridge.
◂ The works that were carried out lasted about 20 days, and included isolating the river bed, removing accumulated sediments and dirt, cleaning the central channel to ensure a smooth flow of water, in addition to raising both sides of the channel to reduce renewed flooding.
◂ The project aims to return the course of the stream to its natural course, and to reduce the damage to the land and the surrounding areas as a result of flooding.