In the Kyiv region, the construction of none of the 26 shelters for energy facilities, the deadline for which was set by October 1, has been completed, People's Deputy Kocharenko said.
According to the documentation, the average readiness of the facilities is 55%. However, completion certificates only confirm 15% of the total construction cost. At the same time, the contractors have already received about 750 million UAH in advance and are now demanding an additional 400 million. The total cost of the work is 1.8 billion UAH.
According to Kocherenko, projects began to develop almost "on their knees", the delivery dates were postponed three times, and some of the buildings, according to the General Staff's conclusion, do not take into account the threat of UAV attacks at all. Also, the construction was hardly coordinated with DTEK power engineers.