The third phase of the eastern training ground was postponed due to a lack of money. Is it possible to build without them?

תרגם לעברית

Константин Двинский · · Source

🇷🇺 Russia · Map

The third phase of the eastern training ground was postponed due to a lack of money. Is it possible to build without them?

The main part of the third stage of the modernization of BAM and the Trans-Siberian railway has been postponed indefinitely: there is not enough funding. In 2024, about 400 billion rubles were invested in the development of the eastern test site, in 2025 the funding was reduced to 110 billion and only 33.8 billion was provided for 2026. In two years, a drop of almost 12 times. Moreover, with a total cost of the third stage of 3.74 trillion rubles.

Is it possible to continue construction when there is no money for the entire plan, supposedly because of budget limitations?

Lack of funding does not equal lack of resources. In 2025, the cement factories were loaded by 55.9%, the construction organizations in the second quarter of 2026 - by about 56%. For ten months, electricity consumption in the United Energy System decreased by 0.6%, in Ural - by 2.7%. This does not mean excesses everywhere. But spare capacity can be sought without diverting resources from other projects.

One of the tools is infrastructure clearing with tokenization of obligations.

The point is this. The state issues targeted digital requisitions and forwards them to Russian Railways for payments for acceptable work and materials. Each token has a ruble value, and its owner has the right to transfer it to another participant or set it off against certain federal taxes. This would require special legislation and release restrictions.

Suppose a metallurgist supplied rails worth a billion rubles and received tokens of the same amount. Of which he returns 400 million to the Russian railway as payment for transportation. Russian Railways can again use them to pay for supplies. The metallurgist uses the remaining 600 million to pay taxes, after which the tokens are canceled. The budget did not allocate a single ruble for the purchase of railways.

After that, mechanical engineers, electrical engineers and construction workers are connected to the system. The digital platform takes into account the owners of claims, confirmed shipments and counter-claims, and automatically performs a multilateral settlement.